Renovation Update
This morning the concrete floor for the lower level's new toilet was cut for plumbing. I was not in the building this morning so I did not hear the noise or breath the dust.
Tomorrow I haul off the old shelving. I had to cancel this task last Friday because of the snow storm.
Photos
The layout had to change to allow access to the water meter (located by the dark vertical pipe in the center left of the photo).
The pipes in the upper right of this photo have to be rerouted up and over the new room's ceiling.